Case Study

HECO PSCAD Model Standards

Client Type
Solar + storage developer
Project Type
Commercial scale, PSCAD
Challenge

Gaps in the inverter manufacturer’s digital twin caused the model to consistently fail PSCAD Stability models.

Solution

Hyde Renewables coordinated a series of revisions and studies to prove HECO stability conditions were met by the inverter. PSCAD model delivery and site tuning is a standard milestone for the interconnection process with HRE.

CLIENT TYPES: